Suppose that a firm just made the first unit of a new product in 800 hours, and the second unit in 560 hours. The firm expects to complete the first 80 units this year. The demand next year is expected to be for 270 units. If management expects their rate of learning to continue for this product, how many total hours will be required to produce the product next year?
Hi there! Click one of our representatives below and we will get back to you as soon as possible.