Sanchez Company’s output for the current period was assigned a $410,000 standard direct labor cost.

Sanchez Company’s output for the current period was assigned a $410,000 standard direct labor cost. The direct labor variances included a $10,250 unfavorable direct labor rate variance and a $4,100 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period?