Requirements
Develop a WBS in MS Project or your chosen PM tool
Notes
Imagine that you are a project manager for a construction company. You must develop a WBS for the Site Preparation phase of this project. Here is a list of tasks.
Task Title Predecessors Duration A Contract Approval — 5 B Site Survey A 5 C Permit Application A 4 D Grading B,C 5 E Sewer Lines B 7 F Base Paving D 3 G City Approval C,F 6 H Final Paving E,G 8